Note: these are in order with most recent at the top. If you want to start at the beginning, click here. to go to the bottom of this page.

Thursday, March 30, 2000

The men and women who brought us the Year 2000 version of the Duluth Aerial Lift Bridge


Above, the men and women who brought us the Year 2000 version of the Duluth Aerial Lift Bridge. Below, the last spire is reattached to the north tower as the crane across the street salutes the bridge.

Thursday, March 30, 2000: The Indiana Harbor came under the 'new' Duluth Aerial Lift Bridge Thursday March 30 at 7:21 PM. Everything worked great except the new horn which is very wimpy. At the left is the Indiana Harbor making her turn into the harbor. In the greeting group, at the left is Paul Johnson, Project Manager for the bridge constuction, center back is Joe Litman, consulting engineer for the project from LHB Engineers and at the right is Dennis Techlin, project foreman. Dennis leaves for his next project in Milwaukee tomorrow morning . In the center is Duluth Shipping News and Marine Museum chief in charge of keeping things going, and everything else, Mary George.

March 29, 2000: At the other end of the man-basket at left is the crane across the Bridge from the Duluth Shipping News.

 

Monday, March 27: Workers made several successful partial lifts Monday afternoon, preparing for installation of the chains early Tuesday morning. Work will close the bridge Tuesday morning for these hours:

1 to 2:30 AM and 2:45 to 3:45 AM

Saturday, March 24: Saturday morning and Jim and Steve from J & S Steel put one of the balance chains together. Four chains will be attached to the two counterweights around 2 AM Tuesday morning. Then a test lift.

Workers were unable to attach the chains and lift the bridge on Sunday morning. Another attempt will be made very early, Tuesday morning. The bridge will be closed to traffic during the following hours on Tuesday morning for this procedure:


1 to 2:30 AM and 2:45 to 3:45 AM

Saturday, March 11, 2000: The crane pulls cable that will be attached to the machine house at one end (on the bridge deck at left and below), and up over the sheave (above) to the counter weight at the other end.

Greetings from "The Crane Across the Street"

3/07/2000
Hello again from "The Crane Across The Street" I heard Duluth was a cold place to be in March. Well today it was almost 70 degrees. When I boomed over the bridge this afternoon, all I could see was long underwear hanging in the warm-up shack on the top of the north side of the bridge. What a great day!

We were able to get all 4 of the 43,000 lb. shives up last week. The longest traffic delay was about 40 minutes. Almost everyone was patient and really didn't want to walk or drive under those while they were being lifted into place. (Click here for the rest of story direct from the Crane Across the Street (from the Duluth Shipping News) Click on picture for a close-up of the crane, the man basket, and the sheaves

High winds on Friday (March 3) kept the third sheave on the ground
Thursday, March 2: The first new sheave goes up.

Wednesday night, March 1, the Duluth Shipping News and the Lake Superior Marine Museum Association hosted an evening of slides and conversation regarding the Aerial Lift Bridge Rehab currently going on. At left, Ken, Nick, Steve and Norm wait for the show to start. Norm, a member of Iron Workers Local #563 does all the work, Steve, the bridge operator makes sure all the work gets done, Nick, the engineer, tells Norm what to do so Steve will be happy when they all leave. Ken takes everybody's picture (except of course for the one above.


The operator's house has a brand new console. Click here for more new stuff.


February 18, 2000: The bridge rehab is now working the late shift as the shipping season is only about one month away.

February 16, 2000: It is hard to believe that in just a few months, the front yard of the Corps of Engineers Building at Canal Park will have green grass instead of cranes and snow and trailers and sheaves.

Monday, January 31, 2000: Lee Popovich of Duluth Steel Fabricators works on a part of the column top that will eventually support the new sheaves when they get moved to the top.


Not all the work on the bridge gets done on the bridge.

Duluth Steel Fabrication has been doing a lot of the specialty work on the new steel beams that will soon be put in place. Above left, Brian Robinson and Dan Grayber prepare a part of one sheave bearing support for welding. Brian is heating up the steel to remove moisture prior to welding. Above right, Dan Wegleitner works on another support. Note that it is at an earlier stage. The same shaped steel is further along in the process at the left and has been welded to other pieces of the support.

Friday, January 28, 2000: Two cranes and one oiler get comfort from the cold from Grandma's Keely Heim. Actually, it is two crane operators. Berit Halverson, second from the left, handles the large crane at the south end of the bridge while his father Dene takes care of the crane at the north end. And yes, Dene's crane is slightly bigger than Berit's (Bear), and Dene also gets to put his arm around Keely. Oiler Kitty Ruzynski maintains Dene's crane and every once in a while, he lets her stay inside his warm cab, while he moves men and material around his end of the bridge site. The crane (operator) takes on all crane questions on the Bridge message board.

January 19, 2000: All of the parts of the bridge that are to be replaced or reworked have been removed. Some have been taken to the junk pile, to be replaced by new equipment (the sheaves). Others have been sent out for rehabilitation (the lift chains).

New equipment is arriving at the site and will be continuously from now on. The above is a lifting girder or support that will be placed on the top of the machinery room. The girder will be attached to the new cables that will move the bridge up and down.

January 21, 2000

The first of four sheaves is delivered to the bridge site

December 31, 1999

Five members of Duluth Ironworkers Local 563 ring out the new year by taking down the last two sheaves from the Lift Bridge. Above, literally, they are Mike 'Rivit' McDevitt and Gene Smith standing on the top girder. Again above, the lower row of 3, is Jim 'Scrap' Meysman, Wayne Elfin and Duane Godbout. At right, group portrait on firmer ground. Click here for larger version of picture.
The last sheave descends from the bridge to the front yard of the Corps of Engineers, only hours before the new Millennium rises.
December 30, 1999: The second of 4 sheaves is taken off the bridge (the round pulley on the left middle above, and hanging from the crane at right). Three of them were taken to a junk yard; the fourth will be placed on the property of the Corps of Engineers in Canal Park. New sheaves will be installed later. The sheaves act as pulleys, allowing the cables that move the bridge up and down to do their work. All the old cables are already off the bridge, as is the balance chain. The cables will be replaced; the balance chain will be inspected and repaired if needed. The two sheaves from the north tower will be taken down on Friday.
The second of 4 sheaves is taken off the bridge. All four are original equipment (from 1929) and all will be replaced.
Tuesday, December 21
Workers are build the platform, beneath the bridge, where painters will paint the underside of the bridge.
December 15, 1999

The balence chain sits in my back yard, waiting for its check-up.
December 15, 1999

Above left, the balance chain attaches to the 450 ton counter weight, normally. At right, workers unhook the chain in preparation for taking it down for a complete inspection.
Friday, December 10, 1999
The crane literally dropped in on Grandmas this morning (Friday, Dec 10). She (he,it) was down to get a new cable and a fresh Amercan Flag.
 
December 9, 1999

At left, Duluth News Tribune staff writer Martiga Lohn interviews crane operator Dene Halvorson for a story that appeared in the Saturday, December 11th paper. Guess what he is pointing at.
Above, the very same crane operator and his oiler.
Friday, December 3, 1999
Two workers take a break from preparing the Lift Bridge for its winter makeover. They are watching the Mecta Sea depart Duluth. The Mecta Sea is better known to Duluthians as the Socrates, a ship that ran aground off Park Point in 1985. The letters are still visible under the new paint marking the ship as the Mecta Sea. This ship was here two years ago, under the name of the Union.
November 26, 1999
Wednesday, December 1, 1999
November 17, 1999
Above, Jim 'Scrap' Meysman guides a girder as the crane prepares to lift it up to the bridge. Scrap is one of the workers who is preparing the Aerial Lift Bridge for its winter repair job. (picture taken from inside Duluth Shipping News World Headquarters). At the other end of the crane, Operating Engineer Dene operates the crane while Operating Engineer Kitty maintains it.
October 20, 1999
On Wednesday, while quietly sitting at my desk, I was jolted awake by what I felt was the end of my time here on earth. Not to worry, it was just the start of the Aerial Lift Bridge millennial repair. Good thing it only happens every 100 years. At the left is the evil machine. It can send out 35,000 pounds per square inch of water at a rate faster than the speed of sound. The bridge will be cleaner when it is over, hopefully later today (Thursday). The machine took a break yesterday to allow the Lita to enter the harbor.
October 9, 1999
September 22, 1999
Dick Larson, Director of Public Works for Duluth, speaks to a gathering of Park Point residents in September about the upcoming rehabilitation of the Lift Bridge.

Kenneth Newhams: World Wide Web Design, Maintenance and Marketing
Contact Information
E-Mail Address: knewhams@duluthshippingnews.com

525 Lake Avenue South
Duluth, MN 55802 USA
Telephone: (218) 722-3119

 
dsnsmsmwithtext.gif (2882 bytes)
© 1999 by Kenneth R. Newhams